Steps for connecting your project

Print

In this section, you will learn more about the process of getting your project connected to the distribution grid. You must work closely with your local distirbution company and the Electrical Safety Authority to get your project connected.

Step 1: Request information

Consult your local distribution company and the Electrical Safety Authority about their requirements.

Step 2: Develop a project plan

Prepare a project plan with all the connection information and confirm that it meets the requirements of your local distribution company and the Electrical Safety Authority.

Step 3: Submit a connection request

Fill out the connection request application and submit it to your local distribution company.

Step 4: Decide to proceed and install

After reviewing the cost to connect to the grid, proceed with the installation of your microFIT project.

Step 5: Electrical Safety Authority inspection

Once the project is installed, schedule and complete a safety inspection.

Step 6: Finalize your connection

Work with your local distribution company to complete the connection of your microFIT project.